Mockingbird Ln Improvements: Lincoln Dr to McDonald Dr

CIP Project No. 2018-03

PROJECT INFORMATION

The Town of Paradise Valley will be installing vertical curb and gutter, new sidewalk, driveways, and bike lanes along Mockingbird Ln from Lincoln Dr to McDonald Dr.

This work is part of the Town’s plan to mitigate right of way erosion due to storm water, upgrade sidewalk ramps for ADA compliance, add new sidewalk where sidewalk does not exist, and install bike lanes. This project was first identified in the Town’s Capital Improvement Program in 2018 to bring this section of Mockingbird Ln up to minor arterial roadway standards per the Town’s General Plan.

SCHEDULE (as of August 2022)

Phase:ScopingDesignEasementsConstruction
Start:July 2021Feb 2022Oct 2022June 2024*

*may occur in 2023 contingent on federal (CMAQ) funding availability

The town has been working with all stakeholders (residents, motorists, bicyclists/pedestrians, utility providers, and funding partners) on the proposed improvements to increase safety and to improve drainage in the area. The Arizona Department of Transportation (ADOT) will administer the construction planned for 2023/2024.

The public outreach process allows the public to provide valuable feedback to the project team, staff, and Town Council.”  “All public meeting information is posted below under Project Links as well as announced via AlertPV (sign-up here for email and/or text alerts for this project). For more information, please contact the project manager shown below.

LOCATION

Mockingbird Ln from Lincoln Dr to McDonald Dr

QUESTIONS

Project Hotline: 480-348-3622

Project Manager: Jason Harris, jharris@paradisevalleyaz.gov

PROJECT LINKS

General Plan - Mobility

Capital Improvement Program (CIP)

Scoping Kick-Off Meeting (Presentation), July 21, 2021

Public Notice (Mailer), Aug 2, 2021

Public Meeting #1 (Mailer, Presentation, Roll Plot), Oct 5, 2021

Public Meeting #2 (Mailer, Presentation), Feb 3, 2022

Public Meeting #3 (Mailer, Presentation) August 24, 2022

Pedestrian/Bicycle Counts Mockingbird Ln at Lincoln Dr (Video AM, Video PM, Counts (Excel)) September 13, 2022 (Note: Videos are 1GB zip files and must be downloaded/viewed on a computer)

Pedestrian/Bicycle Counts Mockingbird Ln at McDonald Dr (Video AM, Video PM, Counts (Excel))September 13, 2022 (Note: Videos are 1GB zip files and must be downloaded/viewed on a computer) 

Site Map

MockingbirdLnImprove

Public Meeting #2 Video Recording

Public Meeting #3 Video Recording